Advance notice of construction work
Advance notice of construction work must be given of all construction works that are expected to take longer than one month and that will employ a total of at least 10 workers, including independent contractors, as well as of all works the scale of which is estimated to exceed 500 person-days of labour.
In the case of construction sites shared by multiple contractors, it is the responsibility of the principal contractor (or similar) to submit a notice on behalf of all the parties involved. The notice must also include information about any subcontractors and suppliers as well as their estimated labour resources.
Submitting notices
Advance notices of construction works can be submitted by printing out and filling in a notice form and sending it by post or e-mail to the Division of Occupational Safety and Health of the Regional State Administrative Agency in whose jurisdiction the works are to be carried out. There is also an online form for notifying the authorities.
Printable form: Advance notice of construction work (pdf, in Finnish) | Contact details for Divisions of Occupational Safety and Health
Online form: Advance notice of construction work (in Finnish)
- Section 48 – Obligation to give a prior notice
Government Decree on the Safety of Construction Work (205/2009)
- Section 4 – Prior notice to the occupational safety and health authority (see Annex 1 for the contents of the notice)